MIL-PRF-12571R
4.1.2 Conformance inspection. Conformance inspection of the
refrigerators shall consist of all the verifications listed in
table I. Sampling for this inspection shall be as specified in
the contract or order (see 6.2)
4.2 Order of verifications. Verifications listed in table I
can be performed in any order except verification tests shall be
conducted in the order shown in table II. The first weatherproof
test shall be conducted before the application of the finish to
the refrigerator. All other verifications listed in table I shall
be done after finishing is completed. A second weatherproof test
shall be done upon completion of all other testing as indicated in
table II.
TABLE II.
Verification test sequence
Test
Requirement
Characteristic
Verification
Sequence Paragraph
Paragraph
1
3.4.2
Weatherproof*
4.3.4.2
2
3.4.1
Shock and vibration
4.3.4.1
3
3.3.2
Transportability
4.3.3.2
4
3.2.3
Drainage and
4.3.2.3
watertightness
5
3.4.3
Storage
4.3.4.3
6
3.4.4
Corrosion resistance 4.3.4.4
7
3.2.1
Heat leakage
4.3.2.1
8
3.4.2
Weatherproof*
4.3.4.2
* See paragraph 4.2
4.3. Verification methods. Verification methods can include
visual examination, measurement, testing, simulation, modeling,
engineering evaluation, component properties analysis,
certification and similarity to previously-approved or previously-
qualified designs.
4.3.1 Verification alternatives. The contractor may propose
alternative test methods, techniques, or equipment, including the
application of statistical process control, tool control, or
cost-effective sampling procedures to verify performance (see
6.4).
10